My team works in 1 week sprints and a former PM set the expectation that everyone no matter if they are new to the team or senior should complete 30 points per sprint and that we can't have one person's sprint values set at a different threshold than the rest. Even if that person is new to the team and will take them longer to complete a task compared to a senior dev. What does Scrum say on thresholds? Personally, I don't think there should be thresholds but rather plan stories based on capacity per individual. Curious if anyone has run into something similar?
↧