I am fairly new Scrum Master over two teams (2 months). I have a mentor that has been teaching me the framework of Scrum. In our recent Sprint Retrospective, my mentor went over how the sprint was a success but the way the work was delivered was not team focused and was not working as a cross functional team. The Development team won't tackling user stories as a team but tackling them as individual pieces of work which caused incremental of work being delivered a week at a time instead of our 1-3 day planned increment release.
↧