Scrum Planning Question from Scrum Open Assessment

Hello everyone,

right now I am preparing for PSM1 and I came across this question.

 

Which three behaviors demonstrate that a team is NOT self-organizing and are NOT following the Scrum Guide?

The following answer is correct:

The Development Team invites external people to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog.

 