It does not happen often, but I was wondering what happens if 2 weeks into a 3 week sprint, the sprint goal has been reached with all items have reached the agreed definition of 'Done'.
Why might this happen?
Perhaps the team has increased their velocity from improving scrum practices, or items that were estimated as X turned out to actually be less work as the sprint backlog emerged during the sprint.