Case of Scrum Review

$
0
0

At the end of Sprint, the company management is dissatisfied with the work done.In the sprint review,they state that the results of the work done are not appropriate for the company's future strategic vision.At the same time,they did not like certain characteristics on the product.On the other side, the development team claims that the work done is positive.They believe that all needed features in product has been delivered correctly and there is no need to cancel project.So,there is a gap between opinion of the head of organization and development team.İn this case,what should have been do