Hi everyone,
I have the following case:
- story was estimated for 8 story points
- didn't deliver the story within the sprint, but 85-90% is done
- story was moved to next sprint
- should we re-estimate the story? (let's say we re-estimated to 3)
- in the sprint review if the story is done than we delivered 3 story point for the complex 8 story points story (initially it was 8 st)
so didn't we loose those 5 story points?