Where is the "high priority process improvement" identified during Sprint Retrospective placed?

$
0
0

Question: TRUE or FALSE: The Scrum Team should choose at least one high priority process improvement, identified during the Sprint Retrospective, and place it in the Product Backlog.

My answer: TRUE

Actual Answer: False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least one high priority process improvement identified in the previous Sprint Retrospective meeting.