Question: TRUE or FALSE: The Scrum Team should choose at least one high priority process improvement, identified during the Sprint Retrospective, and place it in the Product Backlog.
My answer: TRUE
Actual Answer: False, to ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least one high priority process improvement identified in the previous Sprint Retrospective meeting.