Hi everyone,
We're estimating our userstories using storypoints, but some questions arise in planning new sprints.
For example, in our sprint 1 we have the following userstories:
Story A - 3 Storypoints --> Finished
Story B - 8 Storypoints --> Finished
Story C - 5 Storypoints --> Not finished, 80% done, testing left.
Questions (Assumption: the whole team is available for sprint 1 + 2):