Hi,
I would like to ask a question... we are doing 2-week sprints and our scheduled sprint review is on a Friday evening. However, due to bad weather, the product owner and the stakeholder is not available on that day. They are available on Monday evening. As a Scrum Master, should I extend the sprint to accommodate their availability? What should the development team do while waiting for the Sprint Review?
Thanks,
Harley