Hi everyone,
I have just taken over responsibility as a a scrum master and although i have worked under a scrum team before for a year but i always had difficulty in estimating according to story points. So in my first project as a scrum master, I took a risk and though to map story points against hours and it went very well. Here is how i mapped:
Points - Hours
1 2-4
3 4-8
5 8-16
7 16-24
9 24+