Interesting Scrum Question

$
0
0
I came across an interesting question in the PSD Open Assessment that asks what the Development Team should do if, within the Sprint, they discover that they cannot complete all the Product Backlog Items that they took in to the Sprint.

I immediately searched for an answer that said something like "The Development Team should meet with the Product Owner and re-negotiate the content of the Sprint Backlog" but no such answer was available.

The answer that is returned as correct is "Raise it as an impediment with the Scrum Master". And I can sort of see where that answer comes from but it doesn't seem like the right answer, just the best of a bad set of options.

I wonder what others think?