Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. And it is divided in two sections.
I understand is required the Product Owner be for the first part (What can be done this Sprint) but, Might I assume the Product Owner could not be in the second one (How will the chosen work get done)?
Thank you in advance.