Definition of Done vs Sprint Goal

$
0
0
Who is responsible for the Definition of Done. What is the difference between the Definition of Done and Sprint Goal ?

My Thoughts :

Definition of Done - is solely created by Development Team and is used to assess when the work is complete on the product increment.

Sprint Goal - provides the guidance to the Development Team on why it is building the increment.

Both Sprint Goal and Definition of Done cannot be changed per Sprint.


Is the above correct ? Appreciate any feedback on the above.