What belongs solely to the Development Team?

$
0
0
Hi,

here is one question that I was in doubt:

Question:
What belongs solely to the Development Team?

A/ The Sprint Backlog
B/ The Product Backlog
C/ The Definition of Done
D/ The Increment

I thought that the increment also belongs to development team, hence selected A & D, however the answer is only A. Any comments and feedback very welcome.