who creates the Sprint Goal?

$
0
0
Hi All,

I cam across this question from Mikael Lapshin quiz
Who is responsible for crafting the Sprint Goal?
The Scrum Team
The Product Owner
The Scrum Master
The Development Team
The Key Stakeholders

The correct answer given by Mikail is The Scrum Team, but i am bit confused on this because i see the following lines in the Scrum Guide

The Product Owner discusses the objective that the Sprint should achieve and the Product Backlog items that, if completed in the Sprint, would achieve the Sprint Goal.

This means to me that the PO comes with a Sprint goal and a list of PBI items which he thinks associates to the Sprint Goal and discusses about them to the Team

Help me in giving a good answer or correct answer for this

Thanks
Raji