Non-finished, blocked stories

$
0
0

How to handle stories that are not finished within the sprint and blocked by stakeholders not providing necessary feedback?

We had internal discussion with the Team and have no clear way of handling that situation. I found so far three ideas how to deal with: 

1) roll out story to the next sprint and escalate the problem

2) keep notifying stakeholders about blockers and after two/three notifications without response put stories into backlog again and leave it there until feedback is provided