Hi community!
I'm preparing myself to PSM2 certification test and found this mock question online with the correct marked as:
To the Sprint Backlog of the next Sprint.
I answered Product Backlog.
My reasoning is that everything that comes from either the Review or the Retro is added there, and only on the Planning the Scrum Team checks what should be done, based on the Sprint Goal and the value order of the PBI's.
Am I wrong? Should it be mandatory to have "the most impactful improvement" on the next Sprint Backlog?