Burndown Chart Cliff

$
0
0

Hello everyone! 

Our team follows a two-week sprint where:

  • Development occurs during week 1
  • QA happens early week 2
  • Acceptance testing happens mid to late week 2
  • Release happens late week 2

Jira tickets are considered "Done" (and therefore burned down) after acceptance testing passes. This causes our burndown to be pretty flat the first 5-8 days of the sprint, and then we have a large burndown cliff at the end of the sprint when tickets are accepted. 