We have set of product backlog items planned in the sprint. Couple of stories are dependent on each other. Though the 'INVEST' criteria is applied for the stories as much possible, still there is dependency between priority stories because of the functional flow. Only when one is implemented the other can be started. This sometime causes the developers focusing on scope which will not contribute to achieve the sprint goal in the meantime. What could be possible option here.
↧