I had this question in the open assessment. I am not sure what this answer is. The correct answer seems to say Scrum Master is a "management" position = True. Then in the feedback section it seems to say the Scrum Master does not manage a team. Can someone explain the difference for me? I thought the Scrum Master need NOT be a management position.
Scrum Master is a "management" position?
Correct answer: A)
You chose: B)
Missed correct answer A)True
Incorrect answer B)False
Points: 0 out of 1
Feedback:
The Scrum Master manages the Scrum process. If the Scrum Master is not a management position, he or she may not have the influence to remove impediments. The Scrum Master does not manage the team.
Scrum Master is a "management" position?
Correct answer: A)
You chose: B)
Missed correct answer A)True
Incorrect answer B)False
Points: 0 out of 1
Feedback:
The Scrum Master manages the Scrum process. If the Scrum Master is not a management position, he or she may not have the influence to remove impediments. The Scrum Master does not manage the team.