Hi. I´m the PO in a software development enterprise. While testing a sprint (release candidate) we found a minor error not related before (no item in the current going sprint asked to correct that pre-existing issue). But that new error is in the same scope of the Goal of the Sprint and its correction is simple (just 4 hours of development). Nevertheless the development team refuses to append that correction in the current sprint. We´ll have to end the sprint, deliver our software with a known bug, and to fix the bug just in the next Sprint .... It doesn´t make sense for me.