At the end of a Sprint, you find that some of the stories are partially “done” and not fully “done” in terms of the Acceptance Criteria. The team decides to remove the scope that is not completed and put the remaining scope in a new story that is added to the next Sprint and then close the story in the current Sprint. Everyone is happy! The team is happy because they got some credit for the hard-work they put in. The management and leadership are happy because looking at the numbers it appears like the team is making good progress. Is this a good practice?
↧