We are working in two week sprints cycle. My team has delivered 48 story points in previous sprint, and 50 in the recent sprint. The team was in full capacity for both the sprints and their was no holiday. Now, how can we forecast the velocity of upcoming sprint where 3 team members are on planned vacations (1 day for each), 1 Dev is unavailable for entire week and there are two Public holidays. This is just an example that I mentioned.
↧