Hi everyone,
I have a concern that needs your advice.
Currently, Sprint Planning event of my team almost exceeds the timebox defined (12 hours or more instead of 8 hours). The reason is that the Team spends a lot of time reviewing detailed tasks.
Below is our actions in the sprint planning:
1. Pick user stories to do
2. All members will break tasks detailedly for each user story. It will include the estimation for each task.
3. Then, Team will review those tasks broken - all of them - one by one. (this session takes up almost the time).