What would be the best approach for Scrum Master, in case the team is in the last week of sprint and it is identified that 2 of the team members went on sick leave and won't return until the sprint end.
Other team members won't have the bandwidth to take over those impacted stories. PO is highlighted regarding this impediment. Would it be good to deprioritize those stories as those could not be completed in the current sprint?