Hi, I am a scrum master and having tough time in explaining story point based estimation to the team because of following reason - Irrespective of how many story points we assign, we expect the team to commit that they will complete the story in a given sprint if it has been taken up during planning session. Now without translating the effort into mandays and adding buffer for complexity and unpredictability, it is impossible to make such an committment.
D you think such commitment is not even required but then how PO would plan their roll outs for features?