The Professional Product Owner book formulas

$
0
0

Here are two formulas from the book

 

Revisiting the formula that ignored size variance:

50 PBIs (total) / 8 PBIs per Sprint (velocity) 3 2-week Sprints 5 12.5 weeks

When you take into account the size variance of the Product Backlog items by applying points, you end up with a revised end date:

160 points (total) / 19 points per Sprint (velocity) 3 2-week Sprints 5 16.8 weeks

 

I understand the calculations should be as follows:- 