The goal of the sprint is not getting changed, but during the sprint is running, its found that the scope of one of the story is reduced. During sprint planning, that particular story was estimated with highest points and now as scope is reduced, should we re-estimate the points again as now the story is remained with lesser amount of work only?
Kindly suggest!