Apparent contridication in these open assesment Questions

$
0
0
Do these 2 questions contradict each other or am I missing something? I got the first one and missed the second.

Q: During a sprint, the development team determines that it will not be able to finish the complete forecast. Who should be present to review and adjust the sprint work selected?
A: The product owner and the Development team


Q: The dev team should not be interrupted during the sprint, The sprint goal should remain intact. These are conditions that foster creativity. Based on this, which of the following are false?
A: The sprint backlog and its contents are fully formulated in the sprint planning meeting and do not change during the sprint.

My A: The dev team may work with the product owner to remove or add work if it finds it has more or less capacity than it expected.