EPIC added to the Sprint backlog

$
0
0

Hello All - I'm working with one of the Transformation teams who are having their baby steps into Scrum and Agile. During the Sprint planning I observed that PO had EPIC in his backlog with high level estimated (story points) and this was techincal one (migration of database from DataStage to Talend)

I have asked PO that he can't have EPIC directly in the backlog and it should be sliced into doable user stories. As per my knowledge and practice of Scrum from last 2 years, I feel it is not a good practice to have epic in the PBacklog and added to sprint and estimated.

 