Hi all,
I have a story which is estimated with 5 story points. However, mid sprint there has been a change request and a new issue type (change request) has been created that explains that request and is linked to the original story. The CR is estimated with 8 story points. What happens now with the original story and the 5 story points? Can I accept the story once the change request is completed and how do account for the work properly?