Quantcast
Channel: Scrum.org Forum
Viewing all articles
Browse latest Browse all 5648

Sprint start or sprint end fall on a holiday.

$
0
0

Hi Everyone,

How to deal when Sprint start or sprint end fall on a holiday.  

Yes, we should recognize that we do not have  much capacity in this sprint and we can plan accordingly.

But, for example,

say 2 weeks sprint , start 2nd June & ends 16th June.  Assume 14, 15 & 16 are holiday.  As sprint length should be fixed (calendar days),


Viewing all articles
Browse latest Browse all 5648

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>