Looking to adapt agile scrum for a small software development team. Needs some clarification on the overall process. If we decide to go with 2 weeks sprint 10 working days. 8 hours per day per resource
For designer we plan to keep them one sprint ahead so developers have everything they need from design side when they start their sprint. Now their time is divided between R&D, Meetings, Development and Unit testing. Roughly 5-6 hours daily for development. and rest for meetings and unit testing as needed.