Hi guys,
I am attempting Scrum Open Test, here is a question I got stucked
Q: The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity.
The answer I selected is "As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and may grow as the work emerges."
The correct answer is "The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change during the Sprint."