So there is a question from PSPO open assessment:
Which two statements explain why the definition of "Done" is important to the Product Owner?
And one of the correct answers is: It assures the Increment reviewed at the Sprint review is usable so the Product Owner may choose to release it.
I was confused by it, because as cited in The Scrum Guide: "A -Done- increment is required at the Sprint Review."
So as I understand the Increment by its definition should be "Done".
Can someone bring the light on this confusion, please?