Development vs QA Estiomates

$
0
0

Hi

I really appreciate someone's input on the following situation.

Personally i do not believe this is a Unique situation and someone else faced the same challenge before.

Our sprints are 2 weeks and we have 3 Developers and 1 QA on the team.

So the challenge is that in most cases our story has number of points  estimates  has more points for QA vs what has developed estimated.

We do not use relative estimation. We do not use hours. Just points.

Example:

Story is estimate by Development is 2 points of effort estimation.