Hi everyone,
I'm on a team that has a mix of development work, and infrastructure support, and there's been some questions about the correct status for items in our sprints. Specifically we're having trouble with addressing vulnerability remediation tasks that need to be filed as changes as they impact our production network. The filing of the change means that we have ~3 days where the work is defined, but not actionable while we wait for CAB approval, etc., so they question is whether or not we put them in Blocked status during that 3-day window.