I am in the process of learning Scrum. I am planning to take PSM1 exam. When i did open assesment, the really do not underatnd the below question. Can anyone please try to explain with real time scenario.
The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the following is false?
The Sprint Backlog and its contents are fully formulated in the Sprint Planning meeting and do not change during the Sprint.
The Product Owner can help clarify or optimize the Sprint when asked by the Development Team.
As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and may grow as the work emerges.
The Development Team may work with the Product Owner to remove or add work if it finds it has more or less capacity than it expected.
The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the following is false?
The Sprint Backlog and its contents are fully formulated in the Sprint Planning meeting and do not change during the Sprint.
The Product Owner can help clarify or optimize the Sprint when asked by the Development Team.
As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and may grow as the work emerges.
The Development Team may work with the Product Owner to remove or add work if it finds it has more or less capacity than it expected.