I'm getting ready to take the PSM exam but have this nagging question. I hope someone can help me understand please.
The question: The length of a Sprint should be...
(choose the best answer)
A) Short enough to keep the business risk acceptable to the Product Owner.
B) Short enough to be able to synchronize the development work with other business events.
C) No more than one month.
D) All of these answers are correct.
My answer: C- No more than one month. It was wrong!