No story points ..Only Hours.. Will it work ?

$
0
0

If the advantage of story points is just to make sure how much story points of work we can take up in a sprint and nothing more than that then instead of story points can we simply assign hours to story ?

For example - Story A has 3 tasks

Task A - 3 hours

Task B- 2 hours

Task C- 6 hours

So we can assign 11 hours to story A. This is our best guess obviously .

Over the period of time, we will get to know how many hours we as a team can complete on an average.

I would like to know any flip side of this approach. 

 

 