Managing the Product Backlog

$
0
0

Our PO has started to practice ordering the Product Backlog with the high order items on the top i.e. the ones which have the most value and which are needed at the earliest by our stakeholders. However, during the Sprint our team identified a dependency due to which this item is blocked.

Should the item still remain at the top of the backlog even though it is blocked because it is still the most valuable functionality needed or should the item be re-ordered and again be moved to the top when the dependency is removed?