In the current team I'm working with, QA's are estimating their time after/seperate from developers.
A situation manifests whereby developers estimate (8 points) fibonacci and then QA will expect something to take half a day to test then the total number gets bumped to 13 points.
This seems very wrong to me.
Can I confirm that QA should be estimating with the development team as 1 estimate, rather than estimating separately please?
I've always estimated points as a group - this is new to me and seems incorrect.
Thanks