Hi dears
As we know that the user stories have a part for acceptance criteria .. ok?
Now during the sprint review, the scrum team meet and demonstrates the working functionality, then product owner accept or refuse that a specific user story has been done or not
The problem is when the P.O. refuses, and asks for adding extra criteria!!
We have a DEADLINE that has been identified in the RFP
What should we do?
Can we ask for change request?