Hello, all,
Our team has just started using Agile to better estimate our current and future demands.
We use a 2 weeks sprint and we are still monitoring our team performance based on the story points we are able to finish per sprint.
Problem is, for some tasks we depend on other teams and very often we are not able to finish something, not because we ran out of time but because we could not start the task (i.e. task to help consumer UAT tests but they didn't finish the development).