I am an organizational team leader. 2 of my team members participate in a scrum team. The scrum team is running 2-week sprint and scheduled their scrum planning in Thursday morning in every 2 weeks. The time for their scrum planning conflicts with my scheduled weekly team meeting. It means my 2 team members will either absent from their scrum planning or absent from the weekly team meeting. I understand that it is not good to miss scrum planning but the team meeting is important too. I discussed with the scrum master and would like them shift the scrum planning 1 day earlier or later.
↧