We do estimation in terms of hours (No story point to hours mapping).
Example: 1, 2, 3, 5, 8, 13 hours etc.
1.We need to assign hours for below activity. How should we deal with it ?
Everyday, throughout the 2-week sprint, run a script in the morning (2 minutes), gather data at the end of the day (5 minutes) and put it into the spreadsheet (5 minutes). Whenever script fails during the day it needs to be restarted.