Hi Team,
It is written in the scrum guide if a sprint is cancelled, the incomplete product backlog items are re-estimated and put back on the product backlog.
Re-estimating an item is a considerable effort. What is the use of re-estimating it at this stage? My logic is, this item might not be the priority for the
next sprint. It will make sense to re-estimate them, if they become the priority again. Keen to understand the thoughts.
Thanks,
Beenish