Quantcast
Channel: Scrum.org Forum
Viewing all articles
Browse latest Browse all 5648

Burndown charts

$
0
0

Hi everyone,

As I am preparing for PSM1, I have a doubt regarding which I have framed in a question below.

 

Who is responsible for drawing burndown charts?

1. Scrum Team

2. Product Owner

3. Scrum Master

4. Development Team.

 

Also, how frequently the burndown chart is being updated?

 

Thank you.


Viewing all articles
Browse latest Browse all 5648

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>