Why can nothing be added to a sprint by anyone outside the team anymore once the sprint has started?

$
0
0

1. Interference and distraction slows the team's speed dramatically.
2. Because the Trello board can't be changed in a sprint.
3. Because it will increase the cost for the sprint.
4. Because it will decrease the quality of the sprint.

Hi everyone, doing a quiz on Scrum and I am having trouble with this question. 

I believe the answer to be 1. but I feel 4 is also relevant. 