I was preparing to understand different chart/metrics in Scrum. In which I came to a question on project burndown.
The purpose of a project burndown chart is to ?
Options:
A. Identify and communicate upcoming milestones
B. Display the level of effort and resources utilized
C. Identify dependencies between sprints or iterations
D. Display the remaining work across time
I believe correct answer is A. Identify and communicate upcoming milestones, however the mock test refers correct answer as D. Display the remaining work across time